A concrete curb calculator works out how much concrete a curb or curb-and-gutter run needs. It finds the cross-section area from the curb and gutter dimensions, multiplies by the length, divides by 27, then adds waste. Fifty feet of 6 by 18 inch curb with a 24 by 6 inch gutter is about 3.56 cubic yards with waste.
Concrete needed
Calculations run in your browser. Inputs are not sent to our servers; anything you Save stays in this browser only.
Saved results (0)
How to Use the Concrete Curb Calculator
- Enter the run length in feet.
- Enter the curb width and curb height in inches, including the part below grade.
- Add a gutter width and gutter thickness for curb-and-gutter, or leave them 0 for a barrier curb.
- Set a 10 percent waste allowance and a bag size, then read the cubic yards to order.
Here is what each result line means:
| Result | What it means |
|---|---|
| Concrete needed | Total volume in cubic yards, including waste. This is the ordering number. |
| Cubic feet | The same volume in cubic feet, for bag counts and short runs. |
| Cubic meters | The metric volume, for suppliers or plans in SI units. |
| Bags needed | How many bags of the selected size the run takes, rounded up. |
| Weight | Approximate placed weight in short tons. |
| Cross-section area | The end-section area in square feet, which sets how much each foot of run holds. |
What Is a Concrete Curb Calculator?
A concrete curb calculator turns the cross-section and length of a curb into the amount of concrete to order. It handles a plain barrier curb and a combined curb-and-gutter, where a flat gutter pan runs alongside the raised curb.
A curb is the same shape along its whole length, so its volume is the end cross-section area times the run. The tool adds the curb and the gutter sections, converts to cubic yards and bags and adds a waste allowance. To size a driveway or path the curb borders, use the concrete slab calculator; for the mix, the concrete mix calculator.
How the Concrete Curb Calculator Works
Because a curb keeps the same profile along its length, the job is to find the area of that end profile and multiply by the run. The profile is the raised curb rectangle plus, for curb-and-gutter, the flat gutter rectangle.
- Convert each curb and gutter dimension from inches to feet by dividing by 12.
- Multiply curb width by curb height, and add gutter width times gutter thickness, for the cross-section area.
- Multiply the area by the run length for cubic feet, then add the waste allowance.
- Divide by 27 for cubic yards and by the bag yield for a bag count.
For the binder in the mix, the cement calculator sizes the cement.
Concrete Curb Example
Suppose you are pouring 50 feet of curb-and-gutter: a 6 inch wide, 18 inch high curb with a 24 inch wide, 6 inch thick gutter, at 10 percent waste.
Calculation: the curb area is 0.5 x 1.5 = 0.75 sq ft and the gutter is 2 x 0.5 = 1.0 sq ft, so the section is 1.75 sq ft. Volume = 1.75 x 50 = 87.5 cu ft, or 3.24 cubic yards. Adding 10 percent waste gives 96.25 cu ft, about 3.56 cu yd and roughly 161 eighty-pound bags.
The lesson: a modest-looking curb section adds up over a long run, so order ready-mix for anything past a short stretch.
Factors That Change How Much a Curb Needs
Cross-section Size
The whole run holds the same section, so the curb and gutter dimensions set the volume per foot. A taller or wider curb lifts the total along the entire length.
Gutter Pan
Adding a gutter can more than double the section, since the flat pan is often wider than the curb. Include it only if you are pouring curb-and-gutter in one section.
Run Length
Length scales the volume one for one. Measure the full run, following curves by their centre line.
Base and Over-pour
Curb is poured against an earth or gravel base that is rarely perfect, so a waste allowance covers the concrete that fills low spots.
Barrier Curb vs Curb and Gutter
The two common forms are sized the same way, but the gutter adds a second section.
| Measure | Barrier curb | Curb and gutter |
|---|---|---|
| Section | Just the raised curb | Raised curb plus a flat gutter pan |
| How to enter it | Curb width and height, gutter left at 0 | Curb and gutter dimensions both filled |
| Concrete per foot | Less | More, often roughly double |
| Where it is used | Islands, edges and planters | Roadways and parking lots that drain |
For the delivered price of either pour, the concrete cost calculator in the related tools prices it by the yard.
When to Use a Concrete Curb Calculator
Ordering Concrete for a Curb Run
Size the run in cubic yards and add waste before you order, so a slip-form or hand pour runs without stopping.
Pricing a Short Curb or Mower Strip
For a short edge or garden mower strip, the bag count shows how many bags to buy and whether hand mixing is realistic.
Comparing Curb Profiles
The cross-section area lets you compare how much concrete different curb and gutter sections use per foot before you commit.
Common Mistakes When Estimating Curb
1. Using Only the Curb Reveal
The visible reveal is less than the full curb height, which usually extends below grade. Enter the full height, not just the part you see.
2. Forgetting the Gutter
On curb-and-gutter, leaving the gutter at 0 can halve the estimate. Include the gutter width and thickness when you are pouring both in one section.
3. Mixing Up Inches and Feet
Enter the length in feet and the curb and gutter sizes in inches, as the fields are labelled.
4. Measuring a Curve on the Inside
Follow a curved run along its centre line, not the short inside edge, or you will under-measure the length.
5. Treating the Estimate as a Standard
Curb and gutter dimensions, slopes and joints follow your local DOT or municipal standard, not this tool, which only turns a section into volume.
Accuracy and Limitations
The arithmetic is exact for a constant rectangular section; the usefulness depends on the dimensions and length you enter.
What it calculates accurately
- Curb and curb-and-gutter volume in cubic yards, cubic feet and cubic meters
- A combined curb plus gutter cross-section
- Bag counts from a stated bag yield, rounded up, plus weight and the section area
What it does not account for
- Battered faces, chamfers or rounded profiles, which reduce the section slightly
- An uneven base beyond your waste allowance
- Reinforcement, expansion joints and the curb standard
- Delivery, short-load fees and taxes
How We Calculate Your Curb Concrete
Frequently Asked Questions About the Concrete Curb Calculator
How do I calculate concrete for a curb?
Find the cross-section area from the curb width times height, add the gutter width times thickness if any, then multiply by the run length and divide by 27 for cubic yards. Fifty feet of a 1.75 square foot section is about 3.24 cubic yards before waste.
How much concrete is in curb and gutter?
It depends on the section. A 6 by 18 inch curb with a 24 by 6 inch gutter is a 1.75 square foot section, so 50 feet is about 3.24 cubic yards, or 3.56 with a 10 percent allowance. Enter your own dimensions above for the exact figure.
What curb height should I enter?
Enter the full curb height, including the part below grade, not just the visible reveal. A 6 inch reveal often sits on a curb that extends well below the surface, and the concrete fills all of it.
Do I include the gutter in the estimate?
Only if you are pouring a combined curb-and-gutter in one section. Enter the gutter width and thickness for that case; leave them at 0 for a plain barrier curb with no gutter pan.
How many bags of concrete for a curb?
A 50 foot curb-and-gutter run is roughly 161 eighty-pound bags with waste, which is far too many to mix by hand, so a run that size is ready-mix. The tool gives the bag count for your run and bag size, rounded up.
Should I add waste for a curb pour?
Yes, about 10 percent. Curb is poured against an earth or gravel base that is rarely perfect, and slip-forming and hand work both lose some concrete, so a margin keeps the run continuous.
Can I use it for a mower strip or edging?
Yes. A garden mower strip or edging is just a small barrier curb; enter its width and height and leave the gutter at 0. The bag count then tells you how many bags to buy.
Is my data saved?
No. The calculation runs entirely in your browser and nothing you enter is stored or sent anywhere.
Sources
- QUIKRETE Concrete Mix 1101 data sheet (QUIKRETE; bag yields 0.60, 0.45 and 0.30 cu ft).
- National Ready Mixed Concrete Association (NRMCA; ready-mixed concrete and ordering).
- American Cement Association (American Cement Association; concrete flatwork basics).
Related Calculators
Pouring curb or curb-and-gutter?
Explore all concrete calculatorsThis calculator is for general planning and estimating only and is not engineering advice. Curb and gutter sizes, slopes, reinforcement and expansion joints follow your local DOT or municipal standard, not this tool, which estimates the concrete volume from the cross-section you enter. Spotted an error? Let us know.