A monolithic slab calculator works out the concrete for a slab poured in one piece with its perimeter footing. It takes the slab as length by width by thickness and adds a deepened footing around the edge, then a waste allowance. A 12 by 16 foot slab at 4 inches with a 16 inch footing needs about 5.65 cubic yards.
Concrete needed
Calculations run in your browser. Inputs are not sent to our servers; anything you Save stays in this browser only.
Saved results (0)
How to Use the Monolithic Slab Calculator
- Enter the slab length, width and thickness in the fields, length and width in feet and thickness in inches.
- Enter the perimeter footing width and depth in inches; enter 0 for both to pour a flat slab with no footing.
- Set the number of slabs and a 5 to 10 percent waste allowance.
- Read the result: total cubic yards, split into the slab and the footing, plus bags and weight.
Here is what each result line means:
| Result | What it means |
|---|---|
| Concrete needed | Total volume in cubic yards, slab plus footing, including waste. The ordering number. |
| Slab | The field slab volume, length by width by thickness. |
| Perimeter footing | The extra concrete in the deepened edge footing. |
| Bags needed | Bags of the selected size for a hand-mixed pour, rounded up. |
What Is a Monolithic Slab Calculator?
A monolithic slab calculator estimates the concrete for a monolithic slab, a foundation where the floor slab and its perimeter footing are poured together as one piece. It adds the deepened edge footing to the flat slab so the order is right.
A monolithic slab-on-grade is common for sheds, additions, garages and houses on ground that does not freeze deep. The footing around the edge carries the walls and reaches below the frost line, and the whole thing is poured in a single continuous pour. The tool sizes the slab and the footing separately and adds them. For the mix itself, use the concrete mix calculator or the cement calculator, and for mix water the water cement ratio calculator.
How the Monolithic Slab Calculator Works
The field slab is length times width times thickness. The perimeter footing is extra concrete: a deepened strip around the edge, so it is the perimeter length times the footing width times the depth below the slab.
- Find the slab volume in cubic feet from length, width and slab thickness.
- Find the perimeter, 2 times length plus width, and multiply by the footing width and the depth below the slab for the footing volume.
- Add the slab and footing, multiply by the number of slabs, and add the waste allowance.
- Divide by 27 for cubic yards, and by the bag yield for a bag count.
Monolithic Slab Example
Suppose you are pouring a 12 by 16 foot monolithic slab at 4 inches, with a 16 inch wide perimeter footing 16 inches deep, and 10 percent waste.
Calculation: the slab is 12 x 16 x 0.333 = 64 cu ft. The perimeter is 56 feet, and the footing adds 56 x 1.333 x (12 / 12) = 74.67 cu ft. Together that is 138.67 cubic feet, or 152.5 with 10 percent waste, which is 5.65 cu yd, about 255 eighty-pound bags and roughly 11 short tons.
The lesson: the footing is more than half the concrete here, so a monolithic slab uses far more than a flat slab of the same floor area.
Factors That Change the Concrete for a Monolithic Slab
Footing Size
The perimeter footing is often the larger share of the concrete, so its width and depth move the total more than the slab thickness. It must reach below the frost line, which sets the depth.
Frost Depth
In a cold climate the footing goes deeper to sit below frost, which adds a lot of concrete. In a warm climate a shallower footing may be allowed. Local code sets this.
Slab Thickness
The field slab is usually 4 inches; a thicker slab for heavier loads adds concrete across the whole floor area.
Sub-base and Over-dig
The footing trench is rarely cut clean, and the sub-base is never perfectly even, so the real pour beats the geometry. That is what the waste allowance covers.
Monolithic Slab vs Stem Wall Foundation
A monolithic slab pours the slab and footing in one piece, while a stem wall foundation pours footings, then walls, then a separate slab. They suit different sites and climates.
| Measure | Monolithic slab | Stem wall |
|---|---|---|
| Pour | Slab and footing in one | Footing, wall, then slab separately |
| Best for | Level sites, shallow frost | Sloped sites, deep frost |
| Speed and cost | Faster, often cheaper | More steps and forming |
| Frost | Edge footing below frost | Walls carry down to the footing |
This tool sizes the monolithic option. Either way, the footing size and reinforcement come from an engineer or your building code.
When to Use a Monolithic Slab Calculator
Ordering Concrete for a Foundation
Size the slab and footing together in cubic yards and add waste before you order, so the continuous pour does not run short.
Checking the Footing Share
See how much the perimeter footing adds, so the deepened edge is in the order and not a surprise.
Comparing to a Flat Slab
Compare the monolithic volume with a flat slab of the same floor area to see what the integral footing costs in concrete.
Common Mistakes When Estimating a Monolithic Slab
1. Leaving Out the Footing
The perimeter footing is often more than half the concrete. Sizing only the flat slab under-orders a monolithic pour badly.
2. a Footing Shallower than the Frost Line
The footing must reach below frost. Using a shallow depth under-builds the foundation, whatever the volume says.
3. Mixing Up Feet and Inches
Entering the slab or footing sizes in the wrong unit throws the result off. Keep length and width in feet and thicknesses in inches.
4. Forgetting a Waste Allowance
A footing trench over-digs and the sub-base is uneven, so the exact geometry runs short. Keep 5 to 10 percent.
5. Treating the Estimate as a Foundation Design
Volume is not design. The footing size, reinforcement and depth come from an engineer or code, not from this tool.
Accuracy and Limitations
The arithmetic is exact; the usefulness depends on the slab and footing sizes and the waste allowance you enter.
What it calculates accurately
- Slab, perimeter footing and total volume in cubic yards and cubic feet
- Bag counts from a stated bag yield, rounded up, and the weight
- Multiple identical slabs through the quantity field
What it does not account for
- The required footing size, reinforcement or frost depth, which come from an engineer or code
- Interior thickened beams or pads, unless added separately
- An over-dug footing trench or uneven sub-base beyond your waste allowance
- Delivery, short-load fees and taxes
How We Calculate Your Monolithic Slab Concrete
Frequently Asked Questions About Monolithic Slabs
How much concrete do I need for a monolithic slab?
It depends on the slab and the footing. A 12 by 16 foot slab at 4 inches with a 16 inch footing needs about 5.65 cubic yards with waste, where the footing is more than half the concrete. Enter your sizes above for the exact figure.
What is a monolithic slab?
A foundation where the floor slab and the perimeter footing are poured together in one continuous pour, rather than as separate footings, walls and slab. It is common for sheds, additions, garages and houses on level ground with shallow frost.
How deep is the footing on a monolithic slab?
The perimeter footing is often 12 to 24 inches deep and must reach below the local frost line, with a width around 12 to 16 inches. The exact size and reinforcement come from an engineer or your building code, not from a volume estimate.
Why does a monolithic slab use so much concrete?
Because of the perimeter footing. On a small building the deepened edge can be more than half the total concrete, so a monolithic slab uses far more than a flat slab of the same floor area. The tool shows the slab and footing split.
How many bags of concrete for a monolithic slab?
Usually too many to bag: even a small shed slab with a footing runs into the hundreds of bags, so monolithic slabs are almost always a ready-mix pour. The tool shows the bag count mainly for scale.
Monolithic slab or stem wall, which is cheaper?
A monolithic slab is often faster and cheaper on a level site with shallow frost, because it is one pour. A stem wall suits sloped sites and deep frost. The right choice is a site and code decision, not just a concrete-volume one.
Should I add extra concrete for a monolithic slab?
Yes, a 5 to 10 percent waste allowance, and a little more for a rough footing trench. A monolithic pour is continuous, so running short mid-pour risks a cold joint in the foundation.
Is my data saved?
No. The calculation runs entirely in your browser and nothing you enter is stored or sent anywhere.
Sources
- QUIKRETE Concrete Mix 1101 data sheet (QUIKRETE; bag yields 0.60, 0.45 and 0.30 cu ft).
- National Ready Mixed Concrete Association (NRMCA; ready-mixed concrete and ordering for a continuous pour).
- American Cement Association (American Cement Association; concrete and slab-on-grade foundations).
Related Calculators
Pouring a monolithic slab foundation?
Explore all concrete calculatorsThis calculator is for general planning and estimating only and is not engineering advice. A monolithic slab is a foundation: the slab thickness, the footing size, the reinforcement, the frost depth and the sub-base come from an engineer or your local building code, not from this tool, which estimates the concrete volume to order. Spotted an error? Let us know.