How much does excavation cost? The answer depends on the machine, the hours, the soil and where the soil goes. This guide separates dated public figures from calculator settings, so you can read each number for what it is.
Excavation cost depends on machine hours, hauling, disposal by the cubic yard or load, soil type and site access. The public rates read for this guide are dated. Caltrans equipment rates cover April 2017 to March 2018, and Colorado county and California agency disposal prices from 2025 and 2026 use different units. No current production rate was found, so get local quotes.
What Drives Excavation Cost
Four cost drivers shape an excavation bill: machine time, hauling, disposal and access. Machine time is priced per hour. Hauling and disposal are priced per cubic yard or per load, so the unit matters as much as the number.
The Excavation Calculator handles the volume side. Enter the length, width and depth of a pit, pick a soil type and a truck size, and it returns bank and loose cubic yards plus a truck count. It has no machine or rate inputs, so you still need local rates for machines and disposal.
Access touches every step. It affects how long a machine works and how soil leaves the site. None of the sources read for this article puts a number on access, so ask your contractor how they plan for it.
Equipment Rates Are Dated, So Read Them as History
The most detailed public equipment rates read for this article come from California. The Caltrans book covers a period that has ended. Its cover states, “Effective April 1, 2017 through March 31, 2018.”
These are past rates, not current ones. For crawler-mounted hydraulic excavators from Caterpillar, the book lists these hourly rates for 2017 to 2018:
- 304 CR (code 0200): $26.50 per hour
- 320 (code 0310): $70.33 per hour
- 330BL (code 0345): $128.44 per hour
Larger machines cost more per hour. The 330BL rate is about 4.8 times the 304 CR rate (our arithmetic). The text read does not say whether these rates include an operator, so do not assume they do. Labor surcharge, 11 percent for regular and overtime time, is listed separately from equipment rates in the same book.
No 2025-26 Caltrans book was read, and no current production rate table was found. A production rate is how many cubic yards a machine moves per hour.
Disposal and Haul Are Priced by Unit and Jurisdiction
Disposal shows the widest spread. Two government schedules read for this article price similar material in different ways. Larimer County, Colorado prices clean dirt per load. The Western Placer Waste Management Authority, a California joint powers agency, prices inert material, which includes clean dirt, per cubic yard and per ton.
| Source and year | Material | Unit | Rate as printed |
|---|---|---|---|
| Larimer County, CO (2026) | Clean dirt, tandem truck | Per load | $100, surcharge included |
| Larimer County, CO (2026) | Rubble, including dirt, over 1,000 lb per cubic yard | Per cubic yard | $40, plus Colorado surcharge listed separately |
| WPWMA, CA (2025) | Inert, including clean dirt | Per cubic yard | $65.50 |
| WPWMA, CA (2025) | Inert, including clean dirt | Per ton | $65.50 |
The Larimer rubble line applies only to material over 1,000 pounds per cubic yard, so clean dirt may not qualify. Check the county definitions first. The WPWMA sheet’s effective date was not verified. Only its file date, May 22, 2025, is visible.
The construction and demolition line shows the same trap. WPWMA lists it at $25.25 per cubic yard and $109.25 per ton. These measure different units, so they cannot be compared directly.
How Soil Type Changes the Load Count
Soil changes the hauled volume. Digging loosens soil, so the same hole fills more truck space. The calculator adds a swell percentage by soil type: sand 15 percent, earth 25 percent, clay 35 percent, rock 60 percent and topsoil 25 percent, which the page marks as approximate.
These percentages are calculator settings, not source figures. The government sources read for this article do not give swell values, so treat each one as an assumption the tool uses.
The calculator uses three steps. Bank cubic yards equal length x width x depth, divided by 27. Loose cubic yards equal bank cubic yards x (1 + swell). Truck loads equal loose cubic yards divided by truck capacity, rounded up.
- Sample pit. A 20 x 10 x 4 ft earth pit gives 800 / 27 = 29.63 bank cubic yards. At 25 percent swell, 29.63 x 1.25 = 37.04 loose cubic yards. With a 12 cubic yard truck, 37.04 / 12 = 3.09, so 4 loads.
- Same pit in clay. At 35 percent swell, 29.63 x 1.35 = 40.00 loose cubic yards. Then 40.00 / 12 = 3.33, so it still takes 4 loads.
- Sand and gravel. A 30 x 15 x 3 ft pit gives 1,350 / 27 = 50.00 bank cubic yards. At 15 percent swell, that is 57.50 loose cubic yards. With a 14 cubic yard truck, 57.50 / 14 = 4.11, so 5 loads.
The truck sizes come from the calculator’s dropdown, not from a source. The 12 cubic yard truck is the tool’s default.
What One Pit Can Cost to Haul and Dispose
Take the 37.04 loose cubic yard sample pit from above. The same soil can produce very different disposal bills, depending on the schedule and its unit. These lines are arithmetic examples, not quotes.
- WPWMA inert, $65.50 per cubic yard: 37.04 x 65.50 = $2,426.12. The sheet does not say whether loose or bank yards apply.
- Larimer rubble, $40 per cubic yard: 37.04 x 40 = $1,481.60. This line needs material over 1,000 pounds per cubic yard, so check that clean dirt qualifies.
- Larimer clean dirt, $100 per tandem load: 4 loads x $100 = $400. The text read does not say whether a tandem load equals a 12 cubic yard truck.
For this one pit, the illustrative range runs from $400 to $2,426. That spread is the lesson. Jurisdiction, unit and material class can move the bill as much as the volume does.
How to Get a Reliable Local Quote
No current production rate table was found for this article. The Caltrans book read is from 2017 to 2018, so treat every dated figure here as background, not a price.
Ask each contractor to quote in the same units. Good quotes state the price basis (per hour, per cubic yard or per load), the haul distance, the disposal site and the soil type. Confirm the disposal fee with the facility that will take the soil.
Local rules, permits, inspectors, and your engineer or supplier decide what applies to your project. This guide does not replace their advice.
Enter your dimensions and soil type in the pit volume and truck load estimator, then get local rates for the machine, the haul and the disposal site.
FAQs About Excavation Cost
How much does excavation cost per hour?
No 2026 hourly rate was verified. The Caltrans book read lists a Caterpillar 320 excavator at $70.33 per hour for April 2017 to March 2018, with operator inclusion not stated.
Why do disposal prices differ so much between counties?
Each county sets its own material classes, units and years. Larimer County, Colorado prices clean dirt per load, while Western Placer, California prices inert material per cubic yard. Compare only matching units.
How many truck loads does a dig need?
Divide the loose cubic yards by your truck capacity, then round up. A 37.04 loose cubic yard dig in a 12 cubic yard truck needs 4 loads. Your hauler sets the real truck size, so confirm it.
Does clay cost more to excavate than sand?
The sources read do not compare excavation cost by soil type. The calculator uses a 35 percent swell for clay and 15 percent for sand, so clay produces more loose soil to haul.
Are the Caltrans rates current?
No. The Caltrans book read covers April 1, 2017 through March 31, 2018. Newer editions are published, but this article did not read them, so ask your contractor for current rates.
Can I use these numbers in my own budget?
Use them as background only. The figures are dated, regional and public, and they are not quotes. Local rules, permits, inspectors, and your engineer or supplier decide what applies to your project.
How do I get an accurate excavation quote?
Ask two or three local contractors to quote in the same units: per hour, per cubic yard or per load. Ask for the haul distance and disposal site, and confirm the disposal fee with that facility.
Sources and Further Reading
References Used in This Article
- California Department of Transportation, Division of Construction, Labor Surcharge and Equipment Rental Rates (Cost of Equipment Ownership), effective April 1, 2017 through March 31, 2018, accessed 2026-11-15.
- Western Placer Waste Management Authority, “07-2025 WPWMA Price Sheet with HHW” (file Prices_2025, PDF created 2025-05-22). No web link was saved for this sheet; saved copy read 2026-11-15.
- Larimer County, Colorado, Solid Waste Fees, 2026 Fee Schedule, accessed 2026-11-15.
These are dated public figures, not quotes. Local rules, permits, inspectors, and your engineer or supplier decide what applies. Reviewed for accuracy by Prof. Dr. Khalil Mudassar, PhD. Last updated 2026-11-15.