A concrete temperature calculator estimates how warm freshly mixed concrete is from the weight and temperature of its aggregate, cement, water, free moisture and any ice. It uses a heat balance where dry solids carry 0.22 times the heat of water. Aggregate at 95 F, cement at 120 F and water at 80 F mix to about 94 F.
Mixed concrete temperature
Calculations run in your browser. Inputs are not sent to our servers; anything you Save stays in this browser only.
Saved results (0)
How to Use the Concrete Temperature Calculator
- Choose F and lb or C and kg, then enter the temperature of the aggregate, cement and mixing water.
- Enter the weight of the aggregate, cement and added water for the batch, plus any free moisture on the aggregate and any ice.
- Optionally pick a limit to compare with, then read the mixed temperature and the verdict.
Here is what each result means:
| Result | What it means |
|---|---|
| Mixed concrete temperature | The estimated temperature of the concrete right after mixing, from the heat balance of the ingredients. |
| Ice share of mixing water | The part of the total mixing water that goes in as ice. |
| Cooling from the ice | How much lower the result is than the same batch with the ice replaced by liquid water at the water temperature. |
| Margin to limit | How far the result sits under a maximum or over a minimum you chose to compare with. |
What Is a Concrete Temperature Calculator?
A concrete temperature calculator predicts how warm or cold a batch of concrete will be when it comes out of the mixer, using the temperature and weight of each ingredient. Concrete is mostly aggregate, so the stockpile temperature matters most, followed by the mixing water.
Producers and contractors use it to decide whether to chill the water, add ice or heat the water before a pour, because hot concrete loses slump quickly and cold concrete sets and gains strength slowly. It predicts the temperature at the mixer, not the temperature after hauling or in the forms, and it is not a strength calculator. For strength by age, see the concrete curing time calculator, and for the mix water itself the water cement ratio calculator.
How the Concrete Temperature Calculator Works
T = [0.22(Ta Ma + Tc Mc) + Tw Mw + Twa Mwa - 112 Mi] / [0.22(Ma + Mc) + Mw + Mwa + Mi]The equation is a heat balance. Each ingredient contributes its weight times its temperature, and dry aggregate and cement are weighted by 0.22 because they hold less heat than the same weight of water. The Portland Cement Association prints it in degrees F and pounds with a 112 on the ice term, and in degrees C and kilograms with an 80.
- Multiply the aggregate and cement temperatures by their weights, add them, and multiply by 0.22.
- Add the mixing water and free-moisture terms, each a temperature times a weight.
- Subtract 112 times the ice weight (80 in C and kg).
- Divide by 0.22 times the aggregate and cement weight plus the water, free moisture and ice weights.
With no ice the ice terms drop out, which is the usual form of the equation. Ice is counted as replacing mixing water, pound for pound, so enter only the liquid water in the water field. This tool treats the free moisture on the aggregate as being at the aggregate temperature.
Concrete Temperature Example
Take a hot-weather batch with 3,000 lb of aggregate at 95 F, 564 lb of cement at 120 F, 260 lb of mixing water at 80 F and 60 lb of free moisture on the aggregate.
Calculation: the numerator is 0.22 x (95 x 3,000 + 120 x 564) = 0.22 x 352,680 = 77,589.6, plus 80 x 260 = 20,800, plus 95 x 60 = 5,700, which totals 104,089.6. The denominator is 0.22 x (3,000 + 564) = 784.08, plus 260, plus 60, which is 1,104.08. The mix comes out at 94.3 F.
Now replace 100 lb of the water with ice, so 160 lb of liquid water and 100 lb of ice. The numerator becomes 77,589.6 + 80 x 160 + 5,700 – 112 x 100 = 84,889.6, the denominator stays 1,104.08, and the mix drops to 76.9 F, about 17.4 F cooler.
Factors That Change the Mixed Temperature
Aggregate Temperature
Aggregate is the largest share of the batch, so it has the biggest pull. In the worked example, each 1 F change in the aggregate moves the result about 0.65 F, because its weight and its free moisture both count.
Mixing Water Temperature
Water is a small share of the weight but carries far more heat per pound, so each 1 F change in the water moves the result about 0.24 F in the example. It is also the easiest ingredient to chill or heat.
Cement Temperature
Each 1 F change in the cement moves the result about 0.11 F in the example. PCA notes that cement is often about 30 to 70 F warmer than the average ambient air temperature, so measure it instead of guessing.
Ice
Ice cools twice, by being cold and by absorbing heat as it melts, which is why the 112 term is so large. It replaces mixing water pound for pound, and all of it must be melted before discharge.
Free Moisture on the Aggregate
Wet stockpiles add water at the aggregate temperature, which pulls the result toward the aggregate temperature. Enter it so the water and the aggregate are not double counted.
Temperature Limits Quoted from the Sources
The sources give a few limits worth comparing against. They are reference points, and the project specification controls.
| Condition | Limit as stated | Source |
|---|---|---|
| Hot weather, maximum | ACI 301 and ACI 305.1 state a maximum of 95 F, which a project specification can modify | NRMCA TIP 18 |
| Cold weather, section under 12 in | 55 F (13 C) as placed | NRMCA CIP 27 |
| Cold weather, section 12 to 36 in | 50 F (10 C) as placed | NRMCA CIP 27 |
| Cold weather, section 36 to 72 in | 45 F (7 C) as placed | NRMCA CIP 27 |
| Fresh concrete freezes | Below about 25 F (-4 C) | NRMCA CIP 27 |
TIP 18 also advises the producer to target a temperature below the specified maximum to allow for a rise of 1 to 5 F during delivery, and CIP 27 says concrete should not exceed the cold-weather temperatures by more than 20 F. The 35 C used in metric mode is a direct conversion of 95 F, not a figure printed in the source.
Ice vs Chilled Water vs Cooling the Aggregate
Ice gives the biggest cut, chilled water a smaller one, and cooling the aggregate works through the largest share of the batch.
| Method | What the sources say | Practical note |
|---|---|---|
| Ice | NRMCA CIP 12: ice can reduce concrete temperature by up to 20 F (12 C). PCA: usually up to 80% of the mixing water | Weigh it, and make sure it melts before discharge |
| Chilled water | NRMCA CIP 12: up to 10 F (6 C) | Easy to batch, limited by how cold the water can be made |
| Cooling aggregate | CIP 12 lists sprinkling and shading the aggregate | The aggregate is most of the weight, so it matters most |
Mixed concrete that is slow to deliver warms up on the way, which the concrete truck calculator helps plan, and a mix built to set in minutes follows different rules, covered by the fast setting concrete calculator.
When to Use a Concrete Temperature Calculation
Planning a Hot-weather Pour
Check whether the batch will clear the maximum and how much ice or chilled water it would take to get comfortably under it.
Planning a Cold-weather Pour
See how hot the mixing water needs to be for the concrete to reach the minimum for its section size, and whether heating the water alone is enough.
Comparing What to Change
Change one ingredient at a time to see whether the water, the aggregate or the ice gives the most movement for the effort.
Common Mistakes with Concrete Temperature
1. Entering Ice as Part of the Water
The equation counts ice separately. Enter only liquid water in the water field, or the ice is counted twice.
2. Guessing the Cement Temperature
Cement is often warmer than the air, so assuming the ambient temperature can understate the result.
3. Ignoring Free Moisture
Wet aggregate carries water that changes the balance. Leaving it out of a wet stockpile shifts the answer.
4. Mixing Units
Pounds and degrees F go together, as do kilograms and degrees C. The toggle converts the numbers for you, but typing a C temperature in F mode gives nonsense.
5. Treating the Result as the Placed Temperature
The equation gives the temperature at the mixer. Hauling, waiting, forms and weather change it before and after placement.
6. Using It as the Only Check
Measure the concrete as delivered. The estimate helps you plan the batch, not replace the thermometer.
Accuracy and Limitations
The equation is applied exactly; how close it is to the real batch depends on how well you know each temperature and weight.
What it calculates accurately
- The PCA heat-balance temperature for the numbers entered
- The cooling effect of ice substituted for mixing water
- Results in F and lb or C and kg
What it does not account for
- Heat added by mixing and by cement hydration
- Warming or cooling during hauling, waiting and placing
- Admixtures, supplementary materials and aggregate moisture beyond what you enter
- The actual temperature of your concrete, which only a thermometer shows
How We Calculate Concrete Temperature
Frequently Asked Questions About Concrete Temperature
What is the formula for the temperature of fresh concrete?
The Portland Cement Association gives it as a weighted heat balance: 0.22 times the aggregate and cement temperature-weight sums, plus the water and free-moisture terms, minus 112 times the ice weight, divided by 0.22 times the aggregate and cement weight plus the water, free moisture and ice weights, in F and lb.
Why is 0.22 used in the formula?
It weights dry aggregate and cement because they hold less heat per pound than water. The Portland Cement Association equation applies it to the aggregate and cement terms and leaves water at full weight.
How much can ice lower the concrete temperature?
NRMCA says ice can reduce concrete temperature by up to 20 F (12 C), and PCA gives the same figure of about 11 C (20 F), with ice typically used for up to 80 percent of the mixing water. The actual cooling depends on the mix.
How much can chilled water lower it?
NRMCA says chilled water can reduce concrete temperature by up to 10 F (6 C). Ice cools more because melting ice also absorbs heat.
What is the maximum concrete temperature in hot weather?
NRMCA TIP 18 says ACI 301 and ACI 305.1 state a maximum of 95 F, which the project specification can modify. It also advises targeting lower to allow a 1 to 5 F rise during delivery.
What is the minimum concrete temperature in cold weather?
NRMCA CIP 27 recommends 55 F (13 C) as placed for sections under 12 in, 50 F (10 C) for 12 to 36 in, and 45 F (7 C) for 36 to 72 in. Fresh concrete freezes below about 25 F.
Should I count the ice in the water weight?
No. Enter only the liquid water in the water field and the ice in its own field. The equation counts ice as replacing mixing water pound for pound, so counting it in both places double counts it.
Does the result match the temperature at the job site?
Not exactly. It is the temperature right after mixing. NRMCA notes a 1 to 5 F rise during delivery in hot weather, and cold or windy conditions cool the load, so measure what arrives.
Why is my result different from a field reading?
The usual causes are a wrong cement or aggregate temperature, unmeasured free moisture, or heat from mixing and hydration, which the equation leaves out. Check the inputs first, then measure the concrete.
Is my data saved?
No. The calculation runs entirely in your browser and nothing you enter is stored or sent anywhere.
Sources
- Mass Concrete for Buildings and Bridges (EB547) (Portland Cement Association; the heat-balance equation with ice, page 16).
- CIP 27 Cold Weather Concreting (NRMCA; cold-weather minimum temperatures and freezing point).
- TIP 18 Managing Concrete Temperature for Specified Requirements (NRMCA; hot-weather maximum and temperature rise during delivery).
- CIP 12 Hot Weather Concreting (NRMCA; ice and chilled water cooling).
Related Calculators
Planning a pour in hot or cold weather?
Explore all concrete calculatorsThis calculator gives an estimate of the temperature of freshly mixed concrete from the numbers you enter and is not engineering advice. Real concrete also gains or loses heat during mixing, hauling and placing, and the temperature of each ingredient is hard to measure exactly. Temperature limits for your job are set by the project specification and the engineer, not by this page; measure the concrete you actually receive. Spotted an error? Let us know.