Erosion Blanket Installation and Stapling

What keeps an erosion blanket on a bare slope through its first hard rain? Washington State’s Department of Ecology answered bluntly in its 2014 manual: “Installation is critical to the effectiveness of these products.” Good erosion blanket installation means soil contact, a buried top edge, laps facing the right way and enough staples.

Quick Answer

Erosion blanket installation follows the same order in every manual we read: grade smooth, seed, bury the top edge in an anchor trench, unroll without stretching, shingle the laps with the upslope piece on top, and staple to the specified pattern. In channels, start at the downstream end and add check slots about every 25 ft.

Prepare and Seed the Ground Before Any Blanket Goes Down

The goal is complete, direct soil contact. Caltrans (California state highway work) tells crews to grade and shape the slope, remove rocks, clods and other obstructions larger than 1 in, and fill voids. North Carolina’s DEQ (NCDEQ) adds fine-grading gullies and rills.

Seed before the blanket. Caltrans, Washington Ecology, NCDEQ and the University of Michigan campus detail all put seed down first. Caltrans notes one exception: turf reinforcement mats are often seeded after installation. Ecology’s 2014 steps also call for track-walking up and down the slope, then hydromulching with seed and fertilizer.

The agencies disagree on when a blanket is needed. Caltrans lists slopes generally steeper than 3:1, while Ecology and NCDEQ point to slopes of 2:1 or steeper with more than 10 ft of vertical relief. Caltrans adds that blankets do not suit excessively rocky sites or areas that will be mowed. With the slope measured along its face, the erosion control blanket calculator gives a first count of rolls and staples.

How Big Should the Top Anchor Trench Be?

Most sources call for a trench 6 in deep at the top of the slope, but widths, depths and staple spacing vary. NCDEQ is the outlier at about 12 in deep by 6 in wide. Washington Ecology’s 2014 text and its own figure even disagree with each other.

Top anchor and seam rules by source
Source Top anchor Trench staples Side lap End lap
Washington Ecology C122, 2014 edition Text: about 12 in wide x 6 in deep. Figure: 6 x 6 in minimum Text: about every 18 in. Figure: 12 in 2 in min (figure) 6 in min (figure)
NCDEQ Practice 6.17 (North Carolina) About 12 in deep x 6 in wide, blanket 2 to 3 ft over the top 1 ft 3 in min 1 ft
UMich SD-SESC-BLANKET (campus standard) 6 x 6 in, about 36 in extended, 12 in folded back and stapled; or no trench with 3 ft over the crest About 12 in 2 to 4 in 2 to 4 in
Caltrans SS-7 (channels only) 12 in deep x 6 in wide terminal trenches 12 in 3 in min 12 in min

In the UMich method, the blanket is stapled in the trench bottom, backfilled and seeded, then a 12 in flap folds back over and takes another staple row. Trench staples add up. On a slope 60 ft wide at the top, staples every 12 in come to about 61, and Ecology’s 18 in text spacing gives about 41 (our arithmetic).

Which Way Do You Unroll an Erosion Blanket?

Down the slope is the usual instruction, but it is not the only one allowed. UMich allows down or horizontally across, and NCDEQ says down (or along) the slope. Washington Ecology’s 2014 figure allows horizontal strips only on slopes flatter than 3H:1V.

Ecology’s steps have the installer roll the blanket slowly down the slope while walking backwards, stapling as it goes. The blanket should never roll down on its own, because stretching ruins soil contact. Once a blanket is placed, no one walks on it. On slopes steeper than 2.5H:1V, Ecology says installers may need to be roped and harnessed.

Slope blanket layout from top to toe Side view of a slope. 1: anchor trench at the top, NCDEQ about 12 in deep by 6 in wide, UMich 6 by 6 in. 2: blanket runs over the crest, NCDEQ 2 to 3 ft, and UMich needs no trench with 3 ft or more over the crest. 3: end lap with the upslope blanket on top, NCDEQ 1 ft, Washington Ecology 2014 figure 6 in minimum. 4: at the toe, turn the end under 4 in and staple at 12 in, from the Ecology 2014 figure. Dots mark staple rows. Not to scale. Slope blanket layout, top to toe (figures by source) 1 Anchor trench: NCDEQ about 12 in deep x 6 in wide; UMich 6 x 6 in 2 Over the crest: NCDEQ 2 to 3 ft; UMich no trench if 3 ft or more 3 End lap, upslope blanket on top: NCDEQ 1 ft; Ecology fig. 6 in min 4 Toe: turn end under 4 in, staple at 12 in (Ecology 2014 figure) 1 2 3 4 Soil in amber, upper strip dark teal, lower strip teal, navy dots = staple rows. Not to scale.
The upslope strip always laps over the downslope strip, like roof shingles.

Overlaps and Roll Layout in Erosion Blanket Installation

Every source agrees on the shingle rule: where two blankets meet end to end, the upslope blanket goes on top. They differ on lap widths. Side laps are at least 2 in in Ecology’s figure, 2 to 4 in for UMich and at least 3 in for NCDEQ. NCDEQ also wants the lap wide enough for a row of anchors.

A layout shows how much blanket laps and trenches use. Take a slope 60 ft wide and 50 ft long (3,000 sq ft) with 8 ft wide rolls and NCDEQ’s 3 in side lap (our arithmetic):

  • Strips: each covers 8 – 0.25 = 7.75 ft, and 60 / 7.75 = 7.74, so 8 strips.
  • Strip length: 50 ft of slope + 3 ft over the top + 1.5 ft down into and across a 12 x 6 in trench = 54.5 ft.
  • Rolls: on the calculator’s default 8 x 112.5 ft roll setting (check your supplier’s size), two strips fit per roll (109 ft), so 4 rolls.

The calculator’s default run agrees: 3,000 sq ft plus its 10 percent allowance setting is 3,300 sq ft, and 3,300 / 900 = 3.67, so 4 rolls. Narrow slopes differ. A slope 20 ft wide and 75 ft long (1,500 sq ft) needs 2 rolls by area. Its layout needs 3 strips of 79.5 ft, and the two 33 ft leftovers spliced with a 1 ft lap reach only 65 ft. That slope needs 3 rolls.

Which Staples, and How Many?

Staple specs and patterns differ by source. Only American Excelsior, a manufacturer, ties its pattern to slope, and only for one product line.

  • Caltrans SS-7: U-shaped staples of minimum 16 gauge steel wire with 8 in legs and a 2 in crown; all anchors 6 to 18 in long, longer in loose soil; drive flush.
  • NCDEQ 6.17: 11 gauge staples at least 6 in long by 1 in wide, or 12 in wooden stakes; a 3 ft center-to-center pattern, with less on moderate slopes.
  • Washington Ecology (2014): metal U-shaped staples at least 6 in long, longer in sandy soils; pattern per the manufacturer.
  • American Excelsior Premier Straw: 6 in wire in cohesive soil, 8 in wire in non-cohesive soil; 0.9, 1.9 and 2.5 staples per sq yd at 4H:1V, 3H:1V and 2H:1V; heads parallel to the flow.

The UMich detail lists patterns from 0.7 to 3.75 staples per sq yd without tying them to slopes. The calculator’s default 3:1 rate of 1.5 per sq yd gives 500 staples on 3,000 sq ft (333.33 sq yd x 1.5). That rate is a tool setting, not a source figure, so match it to your spec.

Field staples for a 3,000 sq ft slope by source Our arithmetic for 3,000 sq ft, which is 333.33 sq yd, field staples only, rounded up. American Excelsior Premier Straw at 4H:1V, 0.9 per sq yd: 300. NCDEQ 3 ft grid, about 1.0 per sq yd: about 334. American Excelsior at 3H:1V, 1.9 per sq yd: 634. American Excelsior at 2H:1V, 2.5 per sq yd: 834. Trench and seam staples are extra. Field staples for a 3,000 sq ft slope (our arithmetic) 333.33 sq yd, field rows only, rounded up; trench and seam staples are extra AEC Premier Straw, 4:1 0.9 per sq yd 300 NCDEQ 3 ft grid about 1.0 per sq yd about 334 AEC Premier Straw, 3:1 1.9 per sq yd 634 AEC Premier Straw, 2:1 2.5 per sq yd 834 AEC = American Excelsior (manufacturer, one product line). NCDEQ = North Carolina DEQ Practice 6.17.
One slope can take 300 to 834 field staples, depending on whose rule applies.

Installing Blankets in Channels: Start Downstream

In a channel, work from the downstream end upstream, so each new piece laps over the one downstream. Caltrans calls for blankets in channels with flows over 3 ft/s; NCDEQ, where bare-earth velocity will exceed 2 ft/sec in the 2-year event.

  1. Lower trench. Dig a 12 in deep x 6 in wide trench across the channel at the lower end (Caltrans, NCDEQ). Lay the roll end upside down in it, staple at 12 in, backfill and compact.
  2. Unroll upstream. Overlap adjacent rolls at least 3 in. Caltrans adds 4 x 4 in longitudinal slots along each side; NCDEQ uses 6 x 6 in trenches above the water line.
  3. Check slots. Fold the blanket into 6 x 6 in slots across the channel every 25 ft (NCDEQ, Ecology) or 25 to 30 ft (Caltrans), and anchor through both layers. NCDEQ, and Caltrans for non-critical jobs, also accept two closely spaced anchor rows instead.
  4. Splices and top end. Shingle-lap spliced ends at least 12 in with the upstream piece on top. End in a 12 x 6 in terminal trench; NCDEQ brings the mat back over itself with a 2 to 3 ft overlap.

A 100 ft channel gets three check slots, at 25, 50 and 75 ft, plus terminal trenches at both ends (our arithmetic). Caltrans also says not to drive tracked or heavy equipment over the mat.

Inspecting and Repairing Blankets After Rain

NCDEQ sets the clearest schedule: inspect at least weekly and after each rainfall of 1/2 in or more, repair immediately, and keep checking until ground cover is established. Caltrans says to inspect periodically and after significant rain. Ecology’s 2014 text gives standards but no frequency.

  • Ground contact: no erosion beneath the blanket; re-staple loose or damaged areas (Ecology, NCDEQ).
  • Washouts: repair the slope or channel, then reinstall (Caltrans).
  • Drainage: fix erosion caused by poorly controlled drainage (Ecology, NCDEQ).

NCDEQ gives blankets a cover factor of 0.07 in their first six weeks and 0.005 at 6 to 12 months, against 1.00 for bare soil. Its sample 3H:1V slope puts blanket-protected vegetation at about 97 percent effective in year one.

Count rolls and staples for your slope

Enter your slope-face area in the rolls and staples calculator for erosion blankets, then check it against your plan’s staple pattern and strip layout.

FAQs About Erosion Blanket Installation

Do you seed before or after laying an erosion blanket?

Before. Caltrans, NCDEQ, Washington Ecology and the University of Michigan detail all seed first. Caltrans notes that turf reinforcement mats are often seeded after installation.

Can you lay an erosion blanket across the slope instead of down it?

Sometimes. The UMich detail allows down or horizontally across, and NCDEQ says down or along the slope. Washington Ecology’s 2014 figure allows horizontal strips only on slopes flatter than 3H:1V. Follow your plan sheet.

How deep should the anchor trench at the top of a slope be?

Six to 12 inches, depending on the source. NCDEQ asks about 12 in deep by 6 in wide, while UMich and Ecology’s 2014 figure show 6 by 6 in. UMich skips the trench when the blanket runs 3 ft over the crest.

How long should erosion blanket staples be?

At least 6 in under NCDEQ and Ecology guidance. Caltrans specifies 8 in legs, and American Excelsior calls for 8 in wire staples in non-cohesive soil. Loose or sandy soil needs longer anchors.

How many staples does a 3,000 square foot slope need?

Roughly 300 to 834 field staples by our arithmetic: about 334 on NCDEQ’s 3 ft grid, or 300, 634 and 834 on American Excelsior’s Premier Straw patterns at 4:1, 3:1 and 2:1. Trench and seam staples are extra.

Can you walk on an erosion blanket after it is installed?

No. Washington Ecology says no one should walk on a blanket once it is placed, and Caltrans says not to drive tracked or heavy equipment over channel mats. Ecology also warns that stretching a blanket ruins its soil contact.

How often should you inspect a new erosion blanket?

NCDEQ says at least weekly and after every rain of 1/2 in or more, until ground cover is established. Caltrans says periodically and after significant storms. Repair undermined or loose areas right away.

Sources and Further Reading

References Used in This Article

Figures come from the sources listed above, and staple and roll counts are our arithmetic. Your plans, permit, inspector and blanket supplier decide the final layout. Reviewed for accuracy by Prof. Dr. Khalil Mudassar, PhD. Last updated 2026-11-15.