Spread Footing vs Continuous Footing: When to Use Each

Does a post need the same footing as a wall? No. A post and a wall carry load differently, and the 2015 IRC treats them differently too.

Quick Answer

A spread footing is an isolated concrete pad that carries one column or post. A continuous footing is a strip that runs under a wall. The 2015 IRC says exterior walls sit on continuous footings or other approved systems. It allows isolated plain concrete footings under columns only in narrow cases.

Spread Footing vs Continuous Footing by Load

The load decides the footing type. A spread footing carries the point load from one column or post. A continuous footing carries the line load from a wall along its full run.

The spread footing calculator works out the concrete for isolated pads. You enter the pad length, width, thickness and count, and the tool returns volume, bags and rebar. It does not handle wall strips.

Spread and continuous footings by load, layout and quantity (layout definitions from the spread footing tool page; code points from the 2015 IRC)
Footing What it carries Layout How the spread tool counts it
Spread (isolated pad) One column or post One pad per column or post. The tool page also names a combined pad under two or more columns. Pad volume times pad count, plus waste on concrete, then bags and bar length.
Continuous (strip) A wall line A strip under the wall. R403.1 of the 2015 IRC puts exterior walls on continuous footings or other approved systems. Not counted by the spread tool. The tool page points strip mode to the Concrete Footing Calculator.

When the Code Allows an Isolated Footing

The 2015 IRC requires continuous footings under exterior walls, or other approved systems. It allows isolated footings under columns only in a narrow case. This article quotes the 2015 text, a historical copy on the ICC site.

Section R403.1.3.6 holds that narrow case. It says “isolated plain concrete footings supporting columns or pedestals are permitted.” It covers detached one- and two-family dwellings of three stories or less with stud bearing walls.

The 2015 text allows this only under those conditions. The spread footing tool page states no such limit, so check these conditions yourself before you use its output. Local amendments can be stricter. This article did not verify any local rule, so check with your building department.

Which footing type does the load need? A decision flow with one question at the top: does the load come from a column or a wall? A column or post leads to a spread pad, if the R403.1.3.6 conditions apply. A wall leads to a continuous footing under R403.1. The chart is a planning question, not a code rule. Does the load come from a column or a wall? Column or post Spread pad, if R403.1.3.6 conditions apply Wall Continuous footing under the wall (R403.1) Planning question, not a code rule. Confirm the conditions in the code your inspector enforces.
Use this as a planning question. It is not a code rule.

How Each Footing Is Laid Out

In plan view, each spread footing is a separate rectangle under one post. The tool takes one pad length, one pad width and a pad count, so every pad in a run has the same size.

A continuous footing is one long strip that follows the wall line. It is laid out as a run, not as a row of separate pads. This article gives no rule for where a wall meets a column. Ask an engineer about that junction.

Plan view: spread pads and a continuous strip A plan view, not to scale. Four separate square pads sit in a row, one under each post, shown as dark dots. Below them, one long continuous strip runs along the full width of the wall line. The legend says a spread pad sits under one post, and a continuous strip runs under a wall. Plan view, not to scale Continuous strip under the wall line Spread pad under one post Continuous strip under a wall
Spread pads sit under posts. A continuous strip follows the wall.

How the Code Sizes a Column Footing

For piers and columns, the 2015 IRC sizes the footing from the tributary load and the allowable soil pressure. Table R401.4.1 gives presumptive soil bearing values in pounds per square foot (psf). Presumptive means the table assumes the value. It is not a measurement of your site.

The table lists these presumptive values, from the highest to the lowest:

  • Crystalline bedrock: 12,000 psf
  • Sedimentary and foliated rock: 4,000 psf
  • Sandy gravel: 3,000 psf
  • Sand, silty sand or clayey sand: 2,000 psf
  • Clay or silt: 1,500 psf

The pad spreads the column load over an area of soil. The soil value sets how much pressure that soil can take, so softer soil needs a larger footing for the same load.

Load path from column and wall to soil A concept diagram with no values. On the left, a column or post box sits above a spread pad, and the pad sits on the soil. On the right, a wall box sits above a continuous strip, and the strip sits on the soil. Arrows show the load moving down into the soil in both cases. Where the load goes Column or post Spread pad Soil Wall Continuous strip Soil
A concept diagram. It shows no loads or sizes.

Quantities for a Four-Pad Example

The spread footing tool page uses four pads as its worked example. Each pad is 4 ft by 4 ft and 12 in thick, with 10 percent waste. These are the tool’s arithmetic examples, not recommended sizes. Every result below was checked by hand. The tool’s stated defaults are one pad, 12 in rebar spacing, 3 in cover and 10 percent waste. Its bag options are 80 lb, 60 lb and 40 lb bags, which hold 0.60, 0.45 and 0.30 cu ft.

  1. Volume per pad. 4 x 4 x 1 = 16 cu ft. Four pads: 16 x 4 = 64 cu ft.
  2. Add waste. 64 x 1.10 = 70.4 cu ft.
  3. Convert to cubic yards. 70.4 / 27 = 2.607, shown as 2.61 cu yd.
  4. Count bags. An 80 lb bag holds 0.60 cu ft. 70.4 / 0.60 = 117.3, so round up to 118 bags.
  5. Count rebar. Each pad has 4 bars each way at 12 in spacing. Each bar runs the 48 in pad side minus 3 in cover on each end, or 42 in (3.5 ft). Per pad: 8 bars x 3.5 ft = 28 ft. Four pads: 112 ft.

The tool page shows 4 x 4 bars per pad, but it does not state the bar length rule in step 5. That rule is inferred from the output. The tool applies waste to concrete, not to rebar.

The tool page’s FAQ gives a pad thickness range of 10 to 16 inches but cites no source for it. This article does not treat that range as a code rule.

Checks Before You Size a Footing

Start with the code your inspector enforces. The text in this article is a 2015 historical copy, so a newer edition or a local amendment may read differently.

Depth is a separate question. The guide on how deep footings should be covers it, so this article does not restate depth rules.

If your column sits in a sonotube, read the guide on whether sonotubes need a footing. This article does not cover sonotube design.

  • Ask about the wall-to-column junction. This article gives no rule for it, so an engineer should decide.
  • Check local amendments. None were verified here.
  • Match the tool to the load. The spread tool covers isolated pads only.
Test your own pad layout

Enter your pad size, pad count and waste in the pad volume and bar count tool to see concrete, bags and rebar for isolated footings.

FAQs About Spread and Continuous Footings

What is the difference between a spread footing and a continuous footing?

An isolated pad sits under one column or post, and a strip runs along a wall line. The 2015 IRC puts exterior walls on continuous footings, or other approved systems.

Can a column sit on an isolated footing instead of a continuous one?

Only in narrow cases. The 2015 IRC allows isolated plain concrete footings under columns or pedestals in some detached one- and two-family dwellings of three stories or less with stud bearing walls. Check local code.

How does the 2015 IRC size a footing for a column?

For piers and columns, it sizes the footing from the tributary load and the allowable soil pressure. Table R401.4.1 gives presumptive soil values, from 1,500 psf for clay or silt to 12,000 psf for crystalline bedrock.

Which edition of the code does this article quote?

This article quotes the 2015 IRC, Chapter 4 Foundations, a historical copy on the ICC website. The 2021 IRC page could not be read, so no 2021 wording is stated.

Does the spread footing calculator handle wall footings?

No. It handles isolated pads under columns or posts. For strips, the tool page points to the Concrete Footing Calculator.

Does the waste allowance apply to rebar?

No. In the tool’s four-pad example, the 10 percent waste applies to concrete only. The rebar total of 112 ft is shown with no waste added.

How many bags did the four-pad example need?

The example needs 118 bags of 80 lb each, at 0.60 cu ft per bag. The 70.4 cu ft with waste divided by 0.60 is 117.3, rounded up to 118.